Restoration of the pavement of the section of the state main highway A1 Riga (Baltezers) - Estonian border (Ainaži) km 21,030 - 36,297

Customer: VAS “Latvijas Valsts ceļi”

Executant: SIA”VIA”

Type of construction: resurfacing

Construction time: 06.2020. – 08.2020.

Main works performed: leveling of asphalt pavement; construction of hot asphalt wear layer SMA11; edge filling, profiling and sealing; horizontal road markings with thermoplastic or cold-plastic materials; replacement of road surface condition, road surface and pavement temperature sensor; ribbon installation; construction of deformation joints, etc. works.